In terms of system stability, what action is a RAS programmed to take?

Study for the NERC Transmission Operations (TOP) Exam with our multiple choice questions and comprehensive explanations. Prepare effectively and boost your confidence for test day!

A Remedial Action Scheme (RAS) is specifically designed to enhance system stability by automatically responding to certain conditions in the electrical grid. When adverse events or disturbances are detected—such as frequency deviations, voltage issues, or system congestion—the RAS can trigger predefined actions to maintain the balance of supply and demand, thereby preventing cascading failures or blackouts.

In the context of the choices presented, the correct action for a RAS is to trip generation or load based on detected conditions. This means that when specific parameters are exceeded, the RAS can isolate parts of the system by quickly disconnecting generation units or reducing certain loads. This swift response helps maintain the overall integrity and stability of the power system by preventing overloading of certain elements and ensuring the system remains within safe operational limits.

Adjusting generation levels, implementing scheduled outages, or altering transmission routes are important aspects of system operations but are not the primary functions of a RAS. The focus of a RAS is primarily on immediate, reactive measures to stabilize the system when real-time disturbances occur, making the selected answer the most appropriate in the context of ensuring system stability.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy